Renovation Update | Meet PFCU | Pittsford Federal Credit Union

Breaking Ground: Renovation Update

05/2017

The Pittsford Branch Remodel Project continues to progress, and we’re excited to see the changes taking shape.

The first floor (where you’d typically visit for a mortgage question) is almost done, with just a few finishing details to complete. The second floor (the main branch level) is about to undergo some significant change, and along with that change, a bit more inconvenience for members visiting our branch.  We’ll do our best to minimize the inconvenience, as well as the time the branch is in disarray – your patience and understanding will be appreciated.  The third floor is taking shape, with wall framing in place and the installation of the “innards” (plumbing, wiring, ductwork, etc.) continuing each day. 

For all three levels, the elevator is 95% complete (and we’re really looking forward to having that available for members).  The new 24-hour ATM vestibule has also taken its basic shape – but, it will be a few months before that new functionality is available for member use. 

The exterior is really getting close to its final configuration, with stone work and framing nearly complete.

The question we hear most often is, “When will the project be done?” – We wish we knew for sure.  But, right now, our contractor estimates September/October.  If that date changes, we’ll be sure to include an update in a future Newsletter and on the website.

And, again, thank you to all the members that have shown considerable patience and tolerance during this remodel – we appreciate your understanding.

04/2017

Some updates of the exterior progress. You may notice the “brow” detail now wraps the third floor, and the “beam” details are being installed – both vertically and longitudinally (over the windows, over the doors, etc..). The concrete block will eventually be finished with the same stone found elsewhere on the exterior (actually, that stone will also be used in some interior locations as well).

Masons are working on in-filling around the elevator door openings, and they’ve assembled scaffolding outside the front of the building to begin attaching the decorative stone that’s earned so much praise elsewhere on the building.

Exterior stone work continues on the elevator shaft and soon surrounding the front entrance.

02/2017

Our remodeling project for the Pittsford branch continues to progress. Soon, the look of the building will change dramatically as the angled roof sections are replaced by vertical walls and an eave configuration similar to what is currently featured around the rest of the building. A few team members have moved into a mostly-complete section of the lower level, now known as the first floor, and are enjoying their new offices, despite a few things remaining on our contractor’s “To Do” list. Demolition is now underway for the south end of the first floor, so it won’t be long until this level is complete. The elevator shaft has been extended up through the main level, which is now known as the second floor, and preparation for the shaft going up to the new third floor is also moving forward. Once the elevator is completed, we can shift team members to the first floor (along with at least some member traffic) and begin the reconstruction of the main branch area.

A huge “Thank You” is owed to the team members most impacted by the project, as well as the members who have visited us during construction. We realize parking can be somewhat tricky at times, so we appreciate your patience and understanding as the Pittsford branch continues to be fully operational throughout construction.

01/2017

Recent construction progress has brought the elevator shaft up through the second floor, along with the foundation and floor of our new 24‐hour ATM vestibule.

The first floor now has updated windows throughout, along with a new door that will open up on to the rear patio area. Finishes are nearly complete in 6 first‐floor offices, soon allowing three team members to vacate the last remaining “old” offices on the first floor so that the remodel process can expand to the remainder of the area. Furniture for four of the offices is expected to arrive February 1st.

Steel to support the third level floor surrounding the elevator shaft is being fabricated – once installed; the floor joists can be cut, allowing the elevator shaft to continue its climb upward through to the third floor. Exterior lights are mostly in place representing a significant improvement in lighting quantity and quality for members visiting after dark.

11/2016

Rapid progress on the south end of the building, with scaffolding in place, the protective blue wrap, insulation, and a scratch coat can be applied – followed by stone.

Downstairs vestibule walls and closet have been removed, as have the interior finishes of the western exterior wall. 

The current door will be converted to a window, and the space that is two windows will become the new door and two windows.

10/2016

Exterior preparation is underway, including removal of old bushes.  The new ramp is essentially done, with the stone work complete and railing installed. Final color will be nearly black, potentially with some green in it. 

Bathroom walls are white subway tile and look great. Elevator “pit” is really close to being done.  The block walls will extend right up through the floor/ceiling to above the current roof level.

09/2016

Drywall installation is underway, following a bit of "infrastructure" work - rough plumbing, HVAC duct work, under-floor connections, etc. Next they will begin some more under-ground work to establish footers to support the inner structure of the building.

08/2016

Renovation of our Pittsford branch started August 1st with the demolition of the lower level. Work will be done in several stages to disrupt business as little as possible. In the mean time, the Mortgage Department has temporarily relocated to the main level. As you can see in these photos, walls have been torn out, flooring removed, and ceilings taken down to create a blank canvas for the new space.

You Are Leaving Pittsford Federal Credit Union's Site

For your convenience PittsfordFCU.org provides a variety of information on our web site that is not directly related to Pittsford FCU products or services. This information is provided through the use of third party service providers via web links. By accessing these links you will be leaving Pittsford FCU's web site and entering a web site hosted by another party. Pittsford FCU is not responsible for the content of this third party web site. Pittsford FCU does not represent either the third party or the member if the two enter into a transaction. Please be advised that you will no longer be subject to, or under the protection of, the privacy and security policies of Pittsford Federal Credit Union. You are encouraged to review the privacy and security policies of the site you are entering, which may be different than those of Pittsford FCU.

Continue to Site